Wednesday, May 30, 2012

Obtaining Construction Permits and Approvals in Taipei


 
Photo: Taipei 101 under construction

How long does it take to get through the bureaucracy to build a 14.3 million TWD (Taiwan Dollar) warehouse in Taipei? There are various divisions of the local government which oversee various processes. Here is a summary of some basic permit related activities, their approximate duration and costs in TWD:

Define property line and check the boundary: 16 days 4,000
Information about existing utilities: 14 days No charge
Firefighting design approval: 21 days No charge
Building permit: 7 days 19,769
Air pollution protection fee: 1 day 151,217
Inspections: 1 day No charge
Occupancy permit: 6 days 100
Land/building ownership certificate: 18 days 39,618
Water connection: 19 days 25,000

要通過官僚集團構建在臺北 14.3 萬台幣 (臺灣美元) 倉庫採取多長時間?個地方政府的各部門監督各種進程。這裡是一些基本的摘要許可證有關的活動,他們的近似的持續時間和成本在提速調圖: 定義屬性線條和邊界檢 16 天 4,000 現有實用程式有關的資訊: 14 天免費消防設計審批: 21 天免費建築許可證: 7 天 19,769 空氣染保護費: 1 天 151,217 檢 1 天免費入住許可證: 6 天 100/建設土地所有權證書: 18 天 39,618 水連接: 19 天 25,000

Reference: Dealing with Construction Permits in Taiwan, China.